Completed November 2022
New intake, about 1550 metres of pipeline and storage tanks for 30 households in Nakasa.
$118,000approved budget
30households benefiting
FY2021-22financial year
March 2022started
November 2022completed
Rural and Outer Islands Programmeprogramme